南京纬三路过江通道工程技术难点分析 预览 被引量:11

Analysis on Technical Difficulties in Construction of Yangtze River-crossing Tunnel on Weisan Road in Nanjing
在线阅读 下载PDF
收藏 分享 导出
摘要 结合南京纬三路过江通道工程特点和地质条件,分析长距离穿越高渗透、高水压的砂卵石复合地层所面临的开挖面稳定性控制、泥浆成膜、刀盘刀具磨损严重、带压换刀等工程难题,并针对这些难题提出需要开展的高渗透性地层中泥膜的形成、盾构带压开舱方案、泥膜形成机制、高压下泥膜的稳定性和气密性等关键科研课题,为高水压和特长水下隧道的建设提供借鉴。 The difficulties in shield boring through complex sandy cobble ground with high permeability and high water pressure, including stability control of excavation face, filter membrane forming, wearing of cutter head and cutting tools and replacing of cutting tools under hyperbaric conditions, are analyzed. As a result, the topics to be studied, such as filter membrane forming in ground with high permeability, filter membrane forming mechanisms, stability of filter mem-brane and air tightness under hyperbaric conditions and cutting tool replacing under hyperbaric conditions, are presen-ted. The paper can provide reference for the construction of extra-long river-crossing tunnels under high water pressure.
作者 张士龙 ZHANG Shilong (CCCC Tunnel Engineering Company Limited, Beijing 100088, China)
出处 《隧道建设》 2013年第2期147-150,共4页 Tunnel Construction
关键词 过江通道 泥水盾构 高水压 砂卵石地层 开挖面稳定 泥膜 刀具磨损 带压换刀 Yangtze River-crossing tunnel slurry shield high water pressure sandy cobble strata excavation face stability filter membrane cutting tool wearing cutter replacing under hyperbaric condition
  • 相关文献

参考文献12

二级参考文献34

共引文献98

同被引文献82

引证文献11

二级引证文献19

投稿分析
职称考试

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部 意见反馈