资源约束条件下项目群工期优化模型研究 预览

Research on Optimization Model of Project Group Duration Under Resource Constraints
在线阅读 下载PDF
分享 导出
摘要 资源总量受限条件下,当同一资源向多个项目供应时,项目群工期压缩原理与方法有别于单项目的工期压缩,不仅面临着有限资源合理分配问题,还需要考虑项目群中各合同项目之间的逻辑关系,为此,需要研究资源有限情况下项目群工期优化问题。借鉴单个项目工期优化方法,考虑项目群内部合同项目之间的逻辑关系,利用资源在项目群内部合同项目之间的转移,构建资源约束条件下项目群工期优化模型,确定可以进行资源输出和输入的合同项目,最终达到项目群工期优化的目的。以期为解决项目群工期优化问题提供新的思路和决策依据。 Under the condition of limited total resources, when the same resource is supplied to multiple projects, the principle and method of project group duration compression is different from that of single project, and not only faces the problem of reasonable allocation of limited resources, it is also necessary to consider the logical relationship between the contract items in the project group. Therefore, it is necessary to study the optimization of the project group duration under the condition of limited resources. Based on the optimization m ethod of single project duration, considering the logical relationship between the internal contract items in the project group, and using the transfer of resources betw een the contract items within the project group, this paper constructs the optimization model of the project group duration under the condition of resource constraints, determine the contract items that can output and input resources, and finally achieve the purpose of project group duration optimization. The purpose of this paper is to provide new ideas and decision-m aking basis for solving the problem of project group construction period optimization.
作者 丰景春 李雪名 丰慧 李明 张可 薛松 Feng Jingchui;Li Xueming;Feng Hui;Li Ming;Zhang Ke;Xue Song(Hohai University Business School,Nanjing 211100,China;Jiangsu Provincial Collaborative Innovation Center of World Water Valley and Water Ecological Civilization,Nanjing 211100,China;Hohai University Institute of Project Management,Nanjing 211100,China;Hohai University International River Research Centre,Nanjing 211100,China)
出处 《科技管理研究》 CSSCI 北大核心 2019年第11期219-225,共7页 Science and Technology Management Research
基金 国家社会科学基金项目“工程建设市场主体社会化监管机制研究”(17BGL156) 国家社会科学基金青年项目“市场决定性作用下PPP项目协同监管模式研究”(15CJL023) 中央高校基本科研业务费专项资金项目“行政审批制度下工程建设政府监管机制创新”(2017B35214).
关键词 资源有限 项目群 NP-HARD 资源转移 limited resources program NP-hard resources transfer
作者简介 通信作者:丰景春(1963—),男,浙江金华人,教授,博士研究生导师,博士,主要研究方向为工程管理与项目管理及其信息化;李雪名(1995-),女,河南平顶山人,硕士研究生,主要研究方向为工程管理与项目管理;丰慧(1989-),女,江苏南京人,博士研究生,主要研究方向为企业多项目管理;李明(1978-),男,山西长治人,讲师,博士,主要研究方向为信息管理与信息系统;张可(1983-),男,河南信阳人,副教授,博士,主要研究方向为系统工程;薛松(1980-),男,安徽淮南人,博士后,主要研究方向为工程管理与项目管理。